News July 9, 2020 LKAB prepares for a twelve-hour stop in Malmberget Regularly scheduled maintenance stops are conducted in the manufacturing industry to ensure quality and safety in the work environment, to …
News June 26, 2020 ”We take the risk of infection seriously” During the past week there have been numerous media reports of a dramatic spread of the coronavirus in Gällivare. A …
News June 25, 2020 One month after the seismic event in the Kiruna mine Inspection of the Kiruna mine continues. Damage is being documented and rock reinforcement work is under way in preparation for …
News June 18, 2020 Tighter restrictions to limit the spread of covid-19 Due to the increased spread of the virus in Norrbotten, LKAB is taking further measures that will apply to all …
News June 18, 2020 LKAB in Malmberget increase safety measures due to COVID-19 LKAB has noticed an increase in the spread of COVID-19 in the municipality, which also affects our own employees.”We have …
News June 15, 2020 Scanning the Kiruna mine Safety must always come first. Therefore, much of the area affected by seismic activity in the mine is being surveyed …
Press release May 29, 2020 LKAB produces Apatite from mine waste in new pilot plant LKAB is developing technology to recycle mine waste to produce phosphorus mineral fertilisers, rare earth elements (REEs), fluorine and gypsum, …
News May 28, 2020 Rock technicians are securing the mine Inspection of the Kiruna mine continues and rock technicians are working all out to solve the seismic puzzle. Damage is …
News May 27, 2020 Production in the Kiruna mine has resumed, but the full extent of damage is undetermined Inspection of the Kiruna mine (KUJ) continues after the major seismic event which occurred on the morning of Monday, May …
News May 19, 2020 Production stopped – inspection of the Kiruna mine is under way Following a seismic event in the Kiruna mine early on Monday morning, intensive inspection of the mine is now under …
Innovative simulation tool for special transports developed in Malmberget What started as two separate projects quickly revealed a shared challenge: transporting large components down to the mine.
Large mining conference in Kiruna seeks solutions for the world’s mineral needs This year, LKAB is the organizer of the Massmin conference together with Luleå University of Technology. Hundreds of mining experts ...
Drilling machines at the Per Geijer deposit vandalized On Friday afternoon, August 30, it was discovered that four drilling machines investigating the Per Geijer deposit in Kiruna had ...